  • In a dispute between a major EPC contractor and the plant owner over alleged schedule delays, performance guarantees, and contract termination related to the construction of a co-generation plant, analyzed the evolution of the other side’s ...

  • Provided expert testimony on behalf of an LNG supplier seeking a price adjustment under an LNG supply agreement. Analyses and testimony covered netback calculations, loss estimates, and the calculation of the embedded option value of the ...

  • Submitted expert testimony on behalf of InterGen in FERC proceedings (Docket No. EC03-131-000) related to Oklahoma Gas & Electric’s proposed acquisition of NRG McClain; analyzed issues of horizontal and vertical market power within the ...

  • Submitted expert testimony on behalf of the Independent Energy Producers Association on vertical market power in FERC proceedings (Docket No. ER04-316-000) related to Southern California Edison’s proposed acquisition of a ...

  • Bates White's Energy Practice's work on a case in Mississippi came to a successful close when the Mississippi Public Service Commission approved a settlement among Mississippi Power Company, the Mississippi Public Utilities Staff, and ...

  • A Bates White expert submitted over 50 pieces of testimony, from 2001 to 2016, at FERC to support refunds for purchases in the California electricity markets related to the California Energy Crisis.  Additionally the expert provided support for ...

  • Testified on behalf of the Virginia State Corporation Commission staff about the use of Smart Meters in a utility Conservation Voltage Reduction (CVR) program designed to reduce electric distribution losses and to conserve energy at customer ...

  • Conducted a comprehensive production cost modeling study on behalf of New York Regional Interconnect, Inc. (NYRI), related to NYRI’s application to the New York Public Service Commission (NYPSC) to construct and maintain a ...

  • Managed the independent reliability needs assessment of the proposed 265-mile 502 Junction-Mt. Storm-Meadow Brook-Loudoun 500 kV Transmission Line for the Virginia State Corporation Commission. The work involved load flow modeling of ...

  • Developed a GIS-based project-siting methodology for utility-scale solar photovoltaic generation facilities. The methodology considers the location of transmission and sub-transmission infrastructure along with known siting ...

  • On behalf of Union Fenosa, a major Spanish energy company, provided technical and regulatory advice regarding a 500-MW wind project in northern Baja California, México, on the technical, commercial, and regulatory aspects of ...

  • Authored the Baja California electricity and natural gas supply and demand forecasts and infrastructure development plans sections of the Energy Supply and Demand Assessment for the Border Region—Consultant Report. The report was ...

Jump to Page

We use cookies to optimize the performance of this site and give you the best user experience. By clicking "Accept," you agree to our use of cookies.

Necessary Cookies

Necessary cookies enable core functionality such as security, network management, and accessibility. You may disable these by changing your browser settings, but this may affect how the website functions.

Analytical Cookies

Analytical cookies help us improve our website by collecting and reporting information on its usage. We access and process information from these cookies at an aggregate level.